Hammerhead Tower Crane
• Max. jib length: 80m; Jib length under different assembling modes can decrease progressively by 10 meters and the Min. jib length is 40 meters.
• Max. lifting capacity 42t;
• Max. hoisting capacity at jib tip: 5.8t;
• Max. lifting moment 800 t.m;
• Max. free-standing height: 75m; Max. working height of anchored crane: 257.4m;
• Hoisting mechanism: QPL4275; power: 132 kW; rope capacity: 1070m;
• Slewing mechanism: HVV145.B1.130C×3; HVV145.B2.130C×1, power: 4×7.5 kW
• Trolleying mechanism: BP185; power: 18.5 kW.
2. Electrical control system
With PLC control, the electrical control system enjoys better reliability and safety. Produced by professional manufacturers with advanced foreign technology, the electrical elements feature service lives that are 3 or 4 times longer than that of domestic products, less faults, easy maintenance and repair as well as reliable operation.
3. Technical features
• The crane boasts of multiple operation modes and wide application;
• The complete machine adopts internationally well-received beautiful shape;
• The crane features high working speed and excellent speed regulation performance. Stepless speed regulation by frequency control, the world's most advanced solution, is adopted for the trolleying mechanism and slewing mechanism, thus ensuring more stable and reliable operation ;
• The cab is independently installed externally with good vision and large inner space, thus offering a good working environment for operators;
• A variety of safety devices are equipped, which are all mechanical or mechatronic products that are applicable to severe working conditions, so as to ensure the tower crane's reliable operation.